Project History
October 2002 | INPEX joins project |
---|---|
June 2006 | Commences crude oil shipments from Ceyhan Terminal |
March 2009 | Completes 1.2 million bbl/d capacity expansion work |
September 2010 | Cumulative export volume reaches 1,000 million bbls |
January 2023 | Cumulative export volume reaches 4,000 million bbls |
The BTC Pipeline is a 1,770-kilometer-long crude oil pipeline that links Baku on Azerbaijan's Caspian Sea coast and Ceyhan in Turkey on the Mediterranean Sea. The pipeline has been fully operational since June 2006. With a transport capacity of 1.2 million barrels per day, the pipeline transports crude oil produced at the ACG Oil Fields in Azerbaijan.