| Contract area (block) | Project status | Production volume | Venture company (established) | Interest owned (*Operator) |
|---|---|---|---|---|
| Darwin, Northern Territory | In production since December 2025 through the Barossa Gas Project |
|
INPEX DLNGPL PTY Ltd (Mar. 19,2003) |
|
Project History
| April 2003 | INPEX joins project through the conclusion of an agreement between shareholders |
|---|---|
| February 2006 | Commences LNG production and shipments |
| March 2022 | JVPs commence FEED for Bayu-Undan CCS to capture and store CO2 emissions by utilizing the Bayu-Undan and Darwin LNG facilities |
| November 2023 | Last LNG cargo lifted from Bayu-Undan Gas supply commences via pipeline to domestic gas customers in Australia through Darwin |
| June 2025 | Production at the Bayu-Undan Gas Condensate Field ceases Gas supply to domestic customers ceases *
FEED work continues at Bayu-Undan CCS
|
| December 2025 | LNG production with gas supplied from the Barossa Gas Field commences
*
Barossa Gas Field in production as of September 2025
|
INPEX produced and shipped condensate, LPG and LNG from the Bayu-Undan Gas Condensate Field from 2004 and supplied gas to domestic customers in Australia from 2006 until production was terminated on June 4, 2025. Meanwhile, Barossa LNG is developing the Barossa Gas Field located in Australian waters off the Northern Territory of Australia and linking it by pipeline to the Darwin liquefied natural gas plant for LNG production, which commenced in December 2025. Currently, INPEX is taking part in studies on reutilizing the depleted Bayu-Undan Gas Condensate Field to capture and store CO₂ emitted from surrounding oil and gas fields, as part of its climate change response initiatives.